- Home
- Government
- Departments
- Public Works
- Engineering Division
- Current Design Projects
Current Design Projects
Kings Road and Alameda Drive Drainage Improvements
The Village previously completed a drainage study for storm sewer and drainage improvements for areas along Kings Road and Alameda Drive. The final design is underway and Right-of-Way and easements are being acquired. Funding for construction will be recommended and considered for FY 2023. Work will consist replacing the existing culverts on Kings Road and Alameda Drive, stream bank stabilization, new storm sewer and high capacity inlets, roadway improvements, street lighting, and restoration.
Kings and Alameda Drainage Study
Lake Marian Woods Water Main Replacement Project
This spring the Village will begin design for the replacement of a 12-inch water main that provides a redundant feed to the eastern portion of the Village. The design will be completed later this year. Funding for construction will be recommended and considered for FY 2023. Work will consist of replacing 3,200 feet of 12-inch water main, water main connections, and restoration
Lake Marian Woods Water Main Replacement Map
Old Town Area 1-A Improvement Project
In 2017, the Village completed a master plan developing options for roadway and utility improvements and anticipated costs that could be used for budget purposes.
The Village started the final design for an area of Old Town identified as Area 1-A in the master plan. This area was chosen as it is the most downstream portion of the drainage area in the master plan area. Proposed storm sewers would be built to serve Area 1-A and upstream areas identified in the master plan. Funding for construction will be discussed as part of future fiscal year budget planning. Work will consist of designing a new curb and gutter roadway with sidewalk, new storm sewer, replacing and up-sizing water mains, sanitary rehabilitation, street lighting, and restoration.
Old Town Phase 2 Improvement Map
Old Town Phase 2 Master Plan Presentation
Lincoln Avenue-Highland Avenue-Hillside Street Reconstruction Project
The design is currently underway for the future reconstruction of these roadways and utilities. Funding for construction will be discussed as part of future fiscal year budget planning. Work will consist of total roadway reconstruction including curb and gutter, new water main and storm sewer, street lighting, pedestrian improvements, and restoration.
Lincoln-Highland-Hillside Project Map
Lincolnwood Manor Area 1 Reconstruction Project
This design is almost complete and construction is anticipated to begin this summer. The Village has received funds through the REBUILD Illinois capital program. Work will consist of total roadway reconstruction including curb and gutter, new storm sewer, street lighting, pedestrian improvements, and restoration.
Lincolnwood Manor Area 1 Project Map
L.W. Besinger Drive Reconstruction Project
The Village was awarded $1,822,000 in Federal Surface Transportation Program funds through the Kane Kendall Council of Mayors. These funds will cover 30% of final design and 70% of construction costs for L.W. Besinger Drive from Ball Avenue to IL-25 including intersection and minor signal improvements.
The preliminary design study is underway. Per federal funding guidelines the Village is required to complete the study that will be reviewed and approved the IDOT. Work will consist of total roadway reconstruction, new curb & gutter and driveway aprons, ADA and pedestrian upgrades, storm sewer improvements, lighting, pavement markings and restoration. The project location map and correspondences sent to the surrounding properties can be view at the links provided below:
L.W. Besinger Drive Project Map
Sample Correspondence
To learn more about the improvement, all are invited to attend the Public Meeting scheduled for Thursday, September 28, 2023 at 6:00PM to 8:00PM hosted by Public Works located in the First Floor Training Room at 1075 Tamarac Drive.