Current Construction Projects

2019 MFT & Capital Westside Resurface Program 

Arrow Road Construction was awarded this project. Work began July 8th with saw cutting for pavement removals of select sidewalk and curb & gutter in the Kimball Farms Subdivision. 

These improvements are funded with both Motor Fuel Tax and Village Capital funds. Work will consist of 2-inch surface removal and replacement, select base repair, select sidewalk and curb & gutter replacement, pedestrian upgrades, ADA complaint upgrades, minor structure maintenance, pavement markings and restoration. Areas include select streets in the Kimball Farms subdivision, South Washington St., Illinois St., Highland Ave., and Hillside St. 

This project is substantially complete with the exception of Highland Ave. Hillside St., Illinois Ave. this will be completed in mid-September and coordinated with work on South Lincoln associated with the IL-31 / Huntley Road Project.

Westside Resurface Map 1

Westside Resurface Map 2

2019 MFT Sidewalk Removal and Replacement Program

Strada Construction Co. was awarded this project. Work began August 5th. 

The Village spends approximate $125k per year in Motor Fuel Tax funds maintaining sidewalks by removing failed sections of sidewalk throughout the Village. Areas of select replacement  for 2019 will be along Sparrow Rd., Hampton Dr., Kingston Cir., Roanoke Ave., and Blue Ridge Dr.  

This project is Complete. 

Sidewalk R & R Map  

2019 CDBG & Capital Eastside Resurface Program

Triggi Construction was awarded this project. Work began July 5th. Sidewalk and curb & gutter replacement is complete along the east side of the roadway. Pavement removal begins July 17th on the west side of the roadway in preparation of the new sidewalk and curb & gutter. 

These improvements are funded with Village Capital funds. Approximately 50% of this project will be reimbursed to the Village with grant funding awarded by the Kane County Community Development fund program. Work will consist of 2-inch surface removal and replacement, select base repair, carriage walk removal, sidewalk and curb & gutter placement, pedestrian upgrades, ADA complaint upgrades, minor structure maintenance, pavement markings and restoration. These improvements will be completed on Navajo Dr. between Helm Rd. and Papoose Rd.

This project is Complete with the exception of the replacement of two brick paver service walks. This work will be completed by mid-September.    

Eastside Resurface Map

Hopi Lane Drainage Improvements

Bolder Construction was awarded this project. Work began August 2nd 

These improvements are located in the neighborhood near the northeast of IL-25 and Helm Road. Work will consist of replacing and up-sizing the existing storm sewer, adding additional storm sewers, water and sanitary improvements, new roadway including curb & gutter and sidewalk. Work is scheduled to begin mid summer.

Construction is on-going. A majority of the water main improvements are complete. Storm sewer improvements are continuing. Once underground improvements are complete, road improvements will begin. This project is on schedule to be completed by mid-November. 

Hopi Lane Storm Sewer Map

Longmeadow Parkway Project

This project is under the jurisdiction of the Kane County Division of Transportation. To obtain updates, status and view exhibits and maps of the overall project limits visit the Kane County Division of Transportation website.

Illinois Route 31 & Huntley Road/Main Street Improvement Project

Visit the dedicated website for updates and status of this construction project.

Huntley Road Improvement Project

This is joint improvement project with the Village of West Dundee with the Village of West Dundee being the lead agency. Visit the Village of West Dundee's website for updates and status of this construction project.